Breakspear Rd South – Road Closure

Saturday, April 5 - Sunday, April 27

From 5 to 27 April 2025, HS2 will be carrying out works on Breakspear Road South, under a full 24-hour road closure north and south of the Network Rail bridge.  During the road closure they will:

  • Remove and replace the culvert, including excavating a trench across the road to install the new drainage pipes
  • Cut sheet piles along the area of the HS2 Breakspear Road bridge
  • Install ditches by excavating and by clearing some vegetation and trees

The following traffic management will be in place:

A full road closure will in place to ensure that the work can be carried out safely.
A clearly signposted diversion route will be in place via Swakeleys Road B467/ High Road B466/ Ickenham Road/ High Street/ Bury Street A4180/ Breakspear Road.
Local access to residential properties will be maintained, however, there will be no through access for emergency services.
Two weeks of the closure will be within the Easter school holiday from 7 to 21 April 2025.

HS2 apologise for any disruption or inconvenience these works may cause.

Details

Start:
Saturday, April 5
End:
Sunday, April 27
Event Category:

By continuing to use the site, you agree to the use of cookies. more information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" then you are consenting to this.

Close